  • Developed cost and resource loaded baseline schedules for four separate runway, taxiway, and service roads improvement projects at LAX international Airport.
  • Successfully applied $250 million dollars’ worth of costs and resources in the master baseline schedules and were received with Owner approval.
  • Generated weekly and monthly updates over five years through multiple phases of project completion.
  • Produced Time Impact Analyses (TIA’s) quantifying the total delay to several interim project completion milestones on behalf of the client.